Installation of CAP at former TSWRB delayed due to wet conditions;
Installation of CAP at former TSWRB delayed due to wet conditions;
Installation of CAP at former TSWRB delayed due to heavy rain yesterday;
Installation of CAP at former TSWRB delayed due to heavy rain in early AM;
Resumed installation of geomembrane cap at North end of CAMU; Reynolds Inliner installed CIPP from SB2 to SB1;
Completed TSWRB closure and final grading at North end of CAMU; Reynolds Inliner conducted Post-CCTV from SB38 to SB40;
Continue TSWRB closure; Reynolds Inliner installed CIPP from SB38 to SB40;
Continue TSWRB closure; Reynolds Inliner installed CIPP from Tk 900 to SB1 and from SB5A to SB5;
Continue TSWRB closure; Reynolds Inliner installed CIPP from SB14 to SB5B;
Continue installation of geosynthetic cap and TSWRB closure; Reynolds Inliner installed CIPP from SB18 to SB14;
Continue installation of geosynthetic cap and TSWRB closure; Reynolds Inliner back onsite and continued OWS CIR activities
Limited crew grading waste and maintaining ditch pumps
Continue cap installation and closure of TSWRB
Continue cap installation; Begin closure of TSWRB
Continue cap installation;
Continue cap installation; Continue OWS point repairs
Continue cap installation; Begin OWS point repairs
Continue installation of geomembrane cap system; Reynolds offsite until 6/20/11
Complete excavation activities at SWMU 7; Reynolds offsite until 6/20/11
Complete excavation activities at SWMU 7; Reynolds offsite until 6/20/11
Begin installation of geomembrane cap on North half of CAMU; Reynolds demobilized until 6/20/11
Continue excavation of area between SWRP and FBP; Reynolds installed CIPP from SB42 to Money Pit
Continue excavation of area between SWRP and FBP; Reynolds prepared to install CIPP from SB42 to Money Pit
Completing SWRP Areas 5/12 and begin area between SWRP and FBP; Reynolds installed CIPP from SB40 to Money Pit
Continued excavation of SWRP Area 5; Reynolds installed CIPP from SB40 to SB37
Continued excavation of SWRP Area 5;
Continued excavation of Area 12 and 5; Reynolds installed CIPP from SB35 to SB37;
Continued excavation of Area 12; Prepared to install CIPP from SB35 to SB37;