Posted July 8, 2011 Daily Report for Thursday June 30, 2011

Installation of CAP at former TSWRB delayed due to wet conditions;


Posted July 8, 2011 Daily Report for Wednesday June 29, 2011

Installation of CAP at former TSWRB delayed due to wet conditions;


Posted July 1, 2011 Daily Report for Tuesday June 28, 2011

Installation of CAP at former TSWRB delayed due to heavy rain yesterday;


Posted July 1, 2011 Daily Report for Monday June 27, 2011

Installation of CAP at former TSWRB delayed due to heavy rain in early AM;


Posted June 30, 2011 Daily Report for Sunday June 26, 2011

Resumed installation of geomembrane cap at North end of CAMU; Reynolds Inliner installed CIPP from SB2 to SB1;


Posted June 30, 2011 Daily Report for Saturday June 25, 2011

Completed TSWRB closure and final grading at North end of CAMU; Reynolds Inliner conducted Post-CCTV from SB38 to SB40;


Posted June 29, 2011 Daily Report for Friday June 24, 2011

Continue TSWRB closure; Reynolds Inliner installed CIPP from SB38 to SB40;


Posted June 29, 2011 Daily Report for Thursday June 23, 2011

Continue TSWRB closure; Reynolds Inliner installed CIPP from Tk 900 to SB1 and from SB5A to SB5;


Posted June 27, 2011 Daily Report for Wednesday June 22, 2011

Continue TSWRB closure; Reynolds Inliner installed CIPP from SB14 to SB5B;


Posted June 27, 2011 Daily Report for Tuesday June 21, 2011

Continue installation of geosynthetic cap and TSWRB closure; Reynolds Inliner installed CIPP from SB18 to SB14;


Posted June 27, 2011 Daily Report for Monday June 20, 2011

Continue installation of geosynthetic cap and TSWRB closure; Reynolds Inliner back onsite and continued OWS CIR activities


Posted June 27, 2011 Daily Report for Saturday June 18, 2011

Limited crew grading waste and maintaining ditch pumps


Posted June 22, 2011 Daily Report for Friday June 17, 2011

Continue cap installation and closure of TSWRB


Posted June 22, 2011 Daily Report for Thursday June 16, 2011

Continue cap installation; Begin closure of TSWRB


Posted June 22, 2011 Daily Report for Wednesday June 15, 2011

Continue cap installation;


Posted June 17, 2011 Daily Report for Tuesday June 14, 2011

Continue cap installation; Continue OWS point repairs


Posted June 17, 2011 Daily Report for Monday June 13, 2011

Continue cap installation; Begin OWS point repairs


Posted June 16, 2011 Daily Report for Saturday June 11, 2011

Continue installation of geomembrane cap system; Reynolds offsite until 6/20/11


Posted June 16, 2011 Daily Report for Friday June 10, 2011

Complete excavation activities at SWMU 7; Reynolds offsite until 6/20/11


Posted June 16, 2011 Daily Report for Friday June 10, 2011

Complete excavation activities at SWMU 7; Reynolds offsite until 6/20/11


Posted June 16, 2011 Daily Report for Thursday June 09, 2011

Begin installation of geomembrane cap on North half of CAMU; Reynolds demobilized until 6/20/11


Posted June 16, 2011 Daily Report for Wednesday June 08, 2011

Continue excavation of area between SWRP and FBP; Reynolds installed CIPP from SB42 to Money Pit


Posted June 16, 2011 Daily Report for Tuesday June 07, 2011

Continue excavation of area between SWRP and FBP; Reynolds prepared to install CIPP from SB42 to Money Pit


Posted June 08, 2011 Daily Report for Monday June 06, 2011

Completing SWRP Areas 5/12 and begin area between SWRP and FBP; Reynolds installed CIPP from SB40 to Money Pit


Posted June 08, 2011 Daily Report for Saturday June 04, 2011

Continued excavation of SWRP Area 5; Reynolds installed CIPP from SB40 to SB37


Posted June 08, 2011 Daily Report for Friday June 03, 2011

Continued excavation of SWRP Area 5;


Posted June 06, 2011 Daily Report for Thursday June 02, 2011

Continued excavation of Area 12 and 5; Reynolds installed CIPP from SB35 to SB37;


Posted June 06, 2011 Daily Report for Wednesday June 01, 2011

Continued excavation of Area 12; Prepared to install CIPP from SB35 to SB37;